What does critical path mean?
In project management, critical path means the longest chain of dependent tasks in a project.
Project Management vocabulary · Schedule & Time
It sets the shortest possible finish date, so any delay to a task on it delays the whole project.
In Turkish: kritik yol
Type at least 2 characters to search all fields.
How it is used
Comes from the critical path method (CPM). Planners calculate it, and managers watch tasks “on the critical path” very closely. Tasks that are not on it have some float, or spare time.
Example sentences
The permit application is on the critical path, so a one-week delay there moves the opening by a week.
Painting isn't on the critical path, so it can wait a few days without affecting the handover.
Common collocations
- on the critical path
- critical path method
- calculate the critical path
- critical path activities
Related terms
This word in other fields
The same English word can have a different meaning in another field:
More terms: Schedule & Time
Practise with graded reading
Reading at the right level is the fastest way to make new words stick. Pick free English books by level:
